N型冷凝泵用于火力发电厂输送冷凝水及类似于冷凝水的其它液体
作者: 浏览次数:

 安装泵

1。拆箱之后检查泵和电机。如果确认无因装卸和运输而造成的损坏和紧固连接松动,泵盖的进出口密封完好,无污垢进入泵内,则可直接送至使用现场进行安装
2。安装泵的基础平面应用水平仪找平。基础水泥固化之后,应将泵安装在基础之上,并用液位计校准底座。应严格检查泵轴和电机轴的同心度。联轴器外圈的允许偏差为0.1mm,两个联轴器端面间隙四周的最大间隙和最小间隙之差不得超过0.3mm
3。泵的吸入管道和排出管道应配备支架,管道的重量不允许直接由泵承担。检查管道、仪表等接口是否密封良好。
Install the pump
1。 Check the pump and motor after unpacking. If it is confirmed that there is no damage and loose fastening connection caused by loading, unloading and transportation, the inlet and outlet of the pump cover are well sealed, and no dirt enters the pump, it can be directly sent to the use site for installation
2。 The foundation plane for installing the pump shall be leveled with a level gauge. After the foundation cement is cured, install the pump on the foundation and calibrate the base with the level gauge. The concentricity of pump shaft and motor shaft should be strictly checked. The allowable deviation of the outer ring of the coupling is 0.1mm, and the difference between the maximum clearance and the minimum clearance around the end clearance of the two couplings shall not exceed 0.3mm
3。 The suction pipe and discharge pipe of the pump shall be equipped with supports, and the weight of the pipe is not allowed to be directly borne by the pump. Check whether the pipeline, instrument and other interfaces are well sealed.